Mechanics Lien Deadlines by State
Published .
A mechanics lien deadline is the last day you can record a lien against the property you improved. Miss it and the lien right is gone, even if the work was done and the invoice is fair.
In most states the clock starts when you last furnish labor or materials to the project. Some states count from completion of the whole project instead, and Texas counts to the 15th day of a later month. The deadline can also depend on who you are. A general contractor hired by the owner may have a different deadline than a subcontractor or supplier further down the chain. Some states also set one deadline for homes and another for commercial work.
Many states require earlier steps to keep the right alive. A preliminary notice may be due soon after you start, and some states require a notice of intent to lien before the lien is recorded. Once the lien is recorded, you must enforce it with a lawsuit within a set time, or it expires.
The table shows each state's headline lien deadline with its notice and enforcement rules. Where the deadline varies, the table says by what. Each state page has the full schedule for every role and project type, and the statute behind it.
Mechanics lien deadlines in all 50 states
| State | Lien deadline | Preliminary notice | Notice of intent | Enforcement |
|---|---|---|---|---|
| Alabama | Within 6 months after last furnishing labor or materials (varies by role) | Not required to preserve lien rights | Required before filing | See the statute |
| Alaska | Within 120 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 6 months after recording |
| Arizona | Within 120 days after completion of the project | Required for every claimant, including the general contractor | Not required | 6 months after recording |
| Arkansas | Within 120 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Required, at least 10 days before filing | 15 months after recording |
| California | Within 90 days after completion of the project | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 90 days after recording |
| Colorado | Within 4 months after last furnishing labor or materials | Not required to preserve lien rights | Required, at least 10 days before filing | 6 months after last furnishing |
| Connecticut | Within 90 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Not required | 1 year after recording |
| Delaware† | Within 6 months after completion of the project (varies by role) | Not required to preserve lien rights | Not required | See the statute |
| Florida | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after recording |
| Georgia | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 365 days after recording |
| Hawaii† | Within 45 days after completion of the project | Not required to preserve lien rights | Not required | See the statute |
| Idaho | Within 90 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Not required | 6 months after recording |
| Illinois | Within 4 months after completion of the project | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 2 years after completion |
| Indiana | Within 60 days after last furnishing labor or materials (varies by project type) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after recording |
| Iowa | Within 90 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Not required | 820 days after last furnishing |
| Kansas | Within 4 months after last furnishing labor or materials (varies by role) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after recording |
| Kentucky | Within 6 months after last furnishing labor or materials | Not required to preserve lien rights | Required, at least 120 days before filing | 1 year after recording |
| Louisiana | Within 60 days after completion of the project | Required for every claimant, including the general contractor | Required, at least 10 days before filing | 1 year after recording |
| Maine | Within 90 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 120 days after last furnishing |
| Maryland† | Within 180 days after last furnishing labor or materials | Not required to preserve lien rights | Required, at least 120 days before filing | See the statute |
| Massachusetts | Within 120 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Not required | 90 days after recording |
| Michigan | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after recording |
| Minnesota | Within 120 days after last furnishing labor or materials | Required for every claimant, including the general contractor | Not required | 1 year after last furnishing |
| Mississippi | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 180 days after recording |
| Missouri | Within 6 months after last furnishing labor or materials | Required for every claimant, including the general contractor | Required, at least 10 days before filing | 6 months after recording |
| Montana | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 2 years after recording |
| Nebraska | Within 120 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 2 years after recording |
| Nevada | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Required, at least 15 days before filing | 6 months after recording |
| New Hampshire | Within 120 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 120 days after last furnishing |
| New Jersey | Within 120 days after last furnishing labor or materials (varies by project type) | Not required to preserve lien rights | Required, at least 60 days before filing | 1 year after last furnishing |
| New Mexico | Within 120 days after completion of the project (varies by role) | Required for sub-subcontractors and suppliers | Not required | 2 years after recording |
| New York | Within 4 months after last furnishing labor or materials (varies by project type) | Not required to preserve lien rights | Not required | 1 year after recording |
| North Carolina | Within 120 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 180 days after last furnishing |
| North Dakota | Within 90 days after last furnishing labor or materials | Not required to preserve lien rights | Required, at least 10 days before filing | 3 years after recording |
| Ohio | Within 60 days after last furnishing labor or materials (varies by project type) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 6 years after recording |
| Oklahoma | Within 4 months after last furnishing labor or materials (varies by role) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after recording |
| Oregon | Within 75 days after last furnishing labor or materials (varies by project type) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 120 days after recording |
| Pennsylvania | Within 6 months after completion of the project | Not required to preserve lien rights | Not required | 2 years after recording |
| Rhode Island | Within 200 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 40 days after the notice of intention is filed |
| South Carolina | Within 90 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 6 months after last furnishing |
| South Dakota | Within 120 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 6 years after last furnishing |
| Tennessee | Within 90 days after completion of the project | Not required to preserve lien rights | Required, at least 90 days before filing | 1 year after completion |
| Texas | By the 15th day of the 3rd month after the month of completion of the project (or delivery of specially fabricated materials, whichever is later) (varies by role) | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 1 year after the last day to file the lien |
| Utah | Within 180 days after completion of the project | Required for every claimant, including the general contractor | Not required | 180 days after recording |
| Vermont | Within 120 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 180 days after recording |
| Virginia | Within 90 days after the end of the month of last furnishing labor or materials (or termination of the contract, whichever is later) | Not required to preserve lien rights | Not required | 6 months after recording |
| Washington | Within 90 days after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 8 months after recording |
| West Virginia | Within 100 days after last furnishing labor or materials | Not required to preserve lien rights | Not required | 6 months after recording |
| Wisconsin | Within 6 months after last furnishing labor or materials | Required for subcontractors, sub-subcontractors, and suppliers | Not required | 2 years after recording |
| Wyoming | Within 150 days after completion of the project (varies by role) | Not required to preserve lien rights | Not required | 180 days after recording |
† Attorney filing. In Delaware, Hawaii and Maryland, the lien is filed through the courts by an attorney.
How to read this table
"Last furnishing" means the last day you performed work or delivered materials under your contract. Small corrections and warranty work often do not count, so use the last day of real work on the job.
Where the deadline varies by project type, the table shows the residential deadline. Where it varies by role, it shows the first claimant group in the state's schedule, usually the general contractor. The state page lists every combination.
If a deadline falls on a weekend or holiday, the statute decides whether it moves to the next business day. Some states extend it and some do not. Plan to record before the date the count lands on.
To turn these rules into calendar dates for your project, use the free mechanics lien deadline calculator. It applies your state's rule for your role and project type to the dates you enter. For the notice that comes first, see preliminary notice requirements by state.
Frequently asked questions
Which states have the shortest mechanics lien deadline?
Which states require a preliminary notice from every claimant?
Which states require a notice of intent to lien?
Does the lien deadline depend on my role or the project type?
Sources
Each row comes from that state's page on this site, which shows the full deadline schedule. These are the statutes those pages cite.
- Alabama: Ala. Code §§ 35-11-213, 35-11-215, 35-11-218, 35-11-221
- Alaska: AS 34.35.064, 34.35.068, 34.35.070, 34.35.071, 34.35.080
- Arizona: A.R.S. §§ 33-992.01, 33-993, 33-998, 33-1002, 33-420
- Arkansas: Ark. Code Ann. §§ 18-44-114, 18-44-115, 18-44-117, 18-44-119
- California: Cal. Civ. Code §§ 8204, 8182, 8412, 8414, 8416, 8460, 8422
- Colorado: C.R.S. §§ 38-22-109, 38-22-110; C.R.S. § 38-35-204
- Connecticut: Conn. Gen. Stat. §§ 49-34, 49-35, 49-39
- Delaware: 25 Del. C. §§ 2711, 2712, 2714
- Florida: Fla. Stat. §§ 713.06, 713.08, 713.18, 713.22, 713.31
- Georgia: O.C.G.A. §§ 44-14-361.1, 44-14-361.5
- Hawaii: HRS § 507-43
- Idaho: Idaho Code §§ 45-507, 45-510, 45-525
- Illinois: 770 ILCS 60/7, 60/9, 60/24
- Indiana: IC 32-28-3-1(h),(i); IC 32-28-3-3; IC 32-28-3-6
- Iowa: Iowa Code §§ 572.8, 572.9, 572.10, 572.11, 572.13, 572.13A, 572.13B, 572.27, 572.28, 572.33
- Kansas: K.S.A. §§ 60-1102, 60-1103, 60-1103a, 60-1103b, 60-1105
- Kentucky: KRS §§ 376.010, 376.080, 376.090, 376.220
- Louisiana: La. R.S. §§ 9:4811, 9:4822, 9:4823, 9:4831, 9:4833
- Maine: 10 M.R.S. §§ 3253, 3255
- Maryland: Md. Code, Real Prop. §§ 9-104, 9-105, 9-109
- Massachusetts: M.G.L. c.254 §§ 4, 8, 11 (and §§2A–2B for substantial completion/termination notices)
- Michigan: MCL 570.1109, 570.1111, 570.1117, 570.1118
- Minnesota: Minn. Stat. §§ 514.011, 514.08, 514.12
- Mississippi: Miss. Code Ann. §§ 85-7-405, 85-7-407, 85-7-409, 85-7-421, 85-7-423, 85-7-429
- Missouri: RSMo §§ 429.012, 429.013, 429.080, 429.100, 429.170, 429.014, 429.016
- Montana: MCA §§ 71-3-531, 71-3-534, 71-3-535, 71-3-533, 71-3-562
- Nebraska: Neb. Rev. Stat. §§ 52-125 to 52-159, including §§ 52-135, 52-137, 52-140, 52-147, 52-157
- Nevada: NRS §§ 108.226, 108.227, 108.228, 108.233, 108.245
- New Hampshire: RSA 447:5, 447:6, 447:8, 447:9, 447:10
- New Jersey: N.J.S.A. §§ 2A:44A-6, 2A:44A-7, 2A:44A-14, 2A:44A-20, 2A:44A-21
- New Mexico: NMSA 1978 §§ 48-2-2.1, 48-2-6, 48-2-10
- New York: NY Lien Law §§ 10, 11, 17, 39, 39-a
- North Carolina: N.C. Gen. Stat. §§ 44A-11.2, 44A-12, 44A-14, 44A-35
- North Dakota: N.D.C.C. §§ 35-27-02, 35-27-13, 35-27-24, 35-27-24.1, 35-27-25
- Ohio: Ohio Rev. Code §§ 1311.05, 1311.06, 1311.13, 1311.04
- Oklahoma: 42 O.S. §§ 142, 143.1, 143.2, 172
- Oregon: ORS §§ 87.021, 87.035, 87.055, 87.039
- Pennsylvania: 49 P.S. §§ 1303, 1502, 1701
- Rhode Island: R.I. Gen. Laws §§ 34-28-4, 34-28-10, 34-28-16
- South Carolina: S.C. Code Ann. §§ 29-5-10, 29-5-90, 29-5-120
- South Dakota: SDCL §§ 44-9-15, 44-9-23, 15-2-13
- Tennessee: T.C.A. §§ 66-11-112, 66-11-115, 66-11-130, 66-11-143, 66-11-145
- Texas: Tex. Prop. Code §§ 53.052, 53.055, 53.056, 53.158
- Utah: Utah Code §§ 38-1a-308, 38-1a-501, 38-1a-502, 38-1a-701
- Vermont: 9 V.S.A. §§ 1921, 1923, 1924, 1925
- Virginia: Va. Code §§ 43-4, 43-5, 43-17
- Washington: RCW 60.04.031, 60.04.081, 60.04.091, 60.04.141
- West Virginia: W. Va. Code §§ 38-2-7, 38-2-8, 38-2-9, 38-2-14, 38-2-34
- Wisconsin: Wis. Stat. §§ 779.02, 779.06, 779.12
- Wyoming: Wyo. Stat. §§ 29-2-106, 29-2-107, 29-2-109
This guide is general information, not legal advice. Lien rules turn on facts specific to your project. Confirm with counsel before relying on them.