Louisiana Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Louisiana construction lien, drawn from La. R.S. §§ 9:4811, 9:4822, 9:4823, 9:4831, 9:4833 and the same rule engine that calculates deadlines for our filing customers.

Louisiana lien rules at a glance

Preliminary notice
Required for every claimant, including the general contractor
Lien filing deadline
within 60 days after completion of the project
Notarization
Not required
No sworn statement or verification is required
Where to record
County recorder where the property sits
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 1 year after the lien is recorded

Who can file a mechanics lien in Louisiana

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Louisiana.

Claimant Lien rights in Louisiana
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Louisiana mechanics lien deadlines

Required for every claimant, including the general contractor. Preliminary notices go to the parish recorder by any method that proves receipt. Louisiana requires a notice of intent to lien before the lien itself is recorded, served at least 10 days ahead of filing.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
General contractors All projects At the contract date (see the notes below for the statutory schedule)

Notice of intent to lien

The final warning before a lien is recorded.

Who Project type Deadline
All claimants All projects At least 10 days before filing the lien

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 60 days after completion of the project

Recording and enforcing a Louisiana lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is not generally available, so build mailing time into the deadline. No notary is required on the lien itself. No sworn statement or verification is required.

After recording

A copy of the recorded lien must be served on the property owner promptly after recording. To keep the lien alive it must be enforced by lawsuit within 1 year after the lien is recorded.

Wrongful lien exposure

Louisiana has no dedicated wrongful-lien penalty statute, but an inflated or baseless lien can still be challenged and removed at the claimant's expense.

Practitioner notes for Louisiana

General preservation deadline: statement of claim/privilege within 60 days after (i) filing of notice of termination or (ii) substantial completion/abandonment if no termination filed (La. R.S. 9:4822(A)). If a timely notice of contract is filed (La. R.S. 9:4811), claimants under 9:4802 must file within 30 days after termination OR within 6 months after substantial completion/abandonment if no termination (9:4822(B)); general contractor then has 60 days after termination OR 7 months after substantial completion/abandonment if no termination (9:4822(C)). Residential (no timely notice of contract): certain claimants may extend to 70 days by giving owner a notice of nonpayment at least 10 days before filing (9:4822(D)) — mapped here as NOI=10 days (conditional). Enforcement: privilege extinguished if suit not filed within 1 year after filing statement (La. R.S. 9:4823(A)(2)); to keep effect against third persons, file notice of pendency within 1 year after statement filing (La. R.S. 9:4833(E)). Notice of contract must be filed before work begins (La. R.S. 9:4811).

Statutory sources: La. R.S. §§ 9:4811, 9:4822, 9:4823, 9:4831, 9:4833. Read the Louisiana lien statute.

File your Louisiana mechanics lien

We calculate the Louisiana deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Louisiana mechanics lien FAQ

How long do I have to file a mechanics lien in Louisiana?
The Louisiana lien must be recorded within 60 days after completion of the project. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Louisiana?
Required for every claimant, including the general contractor. Serve it on the parish recorder by any method that proves receipt. Missing it usually forfeits lien rights for the unnoticed work.
Does a Louisiana mechanics lien need to be notarized?
No. Louisiana does not require a notary on the lien itself. No sworn statement or verification is required.
Where is a mechanics lien filed in Louisiana?
With the county recorder where the property sits. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a Louisiana mechanics lien valid?
A Louisiana lien must be enforced through a foreclosure lawsuit within 1 year after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Is a notice of intent to lien required in Louisiana?
Louisiana requires a notice of intent to lien before the lien itself is recorded, served at least 10 days ahead of filing.
Can a subcontractor file a mechanics lien in Louisiana?
Yes. Subcontractors have lien rights in Louisiana, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.

This page summarizes Louisiana lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.