Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Montana construction lien, drawn from MCA §§ 71-3-531, 71-3-534, 71-3-535, 71-3-533, 71-3-562 and the same rule engine that calculates deadlines for our filing customers.

Montana lien rules at a glance

Preliminary notice
Required for subcontractors, sub-subcontractors, and suppliers
Lien filing deadline
within 90 days after last furnishing labor or materials
Notarization
Not required
No sworn statement or verification is required
Where to record
County recorder where the property sits
E-recording
Available in participating counties
Enforcement deadline
Within 2 years after the lien is recorded

Who can file a mechanics lien in Montana

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Montana.

Claimant Lien rights in Montana
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Montana mechanics lien deadlines

Required for subcontractors, sub-subcontractors, and suppliers. Preliminary notices go to the property owner, with a copy recorded with the county by certified mail.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 20 days after first furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 90 days after last furnishing labor or materials

Montana does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Montana lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is available in participating counties. No notary is required on the lien itself. No sworn statement or verification is required.

After recording

A copy of the recorded lien must be served on the property owner promptly after recording. To keep the lien alive it must be enforced by lawsuit within 2 years after the lien is recorded.

Wrongful lien exposure

Montana has no dedicated wrongful-lien penalty statute, but an inflated or baseless lien can still be challenged and removed at the claimant's expense.

Practitioner notes for Montana

Prelim (Notice of Right to Claim Lien) required for claimants without direct contract with owner; generally due within 20 days of first furnishing (MCA 71-3-531). If notice is late, lien enforceable only for services/materials furnished within 45 days before notice is given (MCA 71-3-531). A copy of the notice must be filed with county clerk/recorder within 5 business days after giving it to the contracting owner (MCA 71-3-531(6)(a)). Lien filing deadline: file lien within 90 days after final furnishing OR within 90 days after owner files a Notice of Completion (MCA 71-3-535(1)). Lien must be served on each owner of record (personal service or certified mail RRR) and certification of service must accompany filing (MCA 71-3-534(2); 71-3-535(2)(b)). Enforcement: action must be commenced within 2 years from filing of lien (MCA 71-3-562).

Statutory sources: MCA §§ 71-3-531, 71-3-534, 71-3-535, 71-3-533, 71-3-562. Read the Montana lien statute.

File your Montana mechanics lien

We calculate the Montana deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Montana mechanics lien FAQ

How long do I have to file a mechanics lien in Montana?
The Montana lien must be recorded within 90 days after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Montana?
Required for subcontractors, sub-subcontractors, and suppliers. Serve it on the property owner, with a copy recorded with the county by certified mail. Missing it usually forfeits lien rights for the unnoticed work.
Does a Montana mechanics lien need to be notarized?
No. Montana does not require a notary on the lien itself. No sworn statement or verification is required.
Where is a mechanics lien filed in Montana?
With the county recorder where the property sits. Electronic recording is available in participating counties, which typically cuts the turnaround to a day or two.
How long is a Montana mechanics lien valid?
A Montana lien must be enforced through a foreclosure lawsuit within 2 years after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Montana?
Yes. Subcontractors have lien rights in Montana, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.