Utah Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Utah construction lien, drawn from Utah Code §§ 38-1a-308, 38-1a-501, 38-1a-502, 38-1a-701 and the same rule engine that calculates deadlines for our filing customers.

Utah lien rules at a glance

Preliminary notice
Required for every claimant, including the general contractor
Lien filing deadline
within 180 days after completion of the project
Notarization
Required
The lien claim must be verified by the claimant
Where to record
County recorder where the property sits
E-recording
Available in participating counties
Enforcement deadline
Within 180 days after the lien is recorded

Who can file a mechanics lien in Utah

Lien rights depend on where you sit in the contracting chain. Tenant-ordered work can reach the owner's interest in Utah only where the owner consented to or required the improvements.

Claimant Lien rights in Utah
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Utah mechanics lien deadlines

Required for every claimant, including the general contractor. Preliminary notices go to the state construction registry by any method that proves receipt.

Calculate your Utah deadlines

Enter your role and project dates to turn the rules below into calendar dates. For other states, use the mechanics lien deadline calculator.

Project type

Choose your role to see which dates you need.

These dates come from the same rules our lien filing service uses. They are not moved for weekends or holidays. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 20 days after first furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 180 days after completion of the project

Utah does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Utah lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is available in participating counties. The lien must be notarized. The lien claim must be verified by the claimant.

After recording

Utah does not require a separate notice after the lien is recorded, though most claimants send one anyway to prompt payment. To keep the lien alive it must be enforced by lawsuit within 180 days after the lien is recorded.

Wrongful lien exposure

Filing a knowingly false lien in Utah can carry criminal penalties as well as civil liability. Intentionally recording a lien notice for more than is due, to cloud title, extract more than is owed or gain an unjustified advantage, is a class B misdemeanor. The filer is also liable to an affected owner, original contractor or subcontractor for twice the excess over the amount actually due or actual damages, whichever is greater.

Practitioner notes for Utah

Utah runs lien notices through the State Construction Registry, an online state database. Anyone who wants a construction lien, including a general contractor, must file a preliminary notice in the registry within 20 days after starting work on the project (Utah Code § 38-1a-501). If you miss that window, a late notice still protects only work done starting 5 days after you file it. A notice filed more than 10 days after a notice of completion has no effect. With no preliminary notice, there is no lien. The notice of construction lien is recorded with the county recorder where the property is located. It is due within 180 days after final completion of the original contract. If a notice of completion is filed in the registry, the deadline becomes 90 days after that filing, but never later than the 180 days (§ 38-1a-502). Within 30 days after recording, deliver or mail a copy to the owner by certified mail. To enforce the lien, file suit within 180 days after recording the lien and record a notice of the pending action within the same period. A lien not enforced in time is void (§ 38-1a-701). Knowingly recording a lien for more than is owed, to cloud title or press for more money, is a class B misdemeanor. The filer also owes twice the overstatement or the actual damages, whichever is greater (§ 38-1a-308). Owner-occupied homes carry added protections under the Residence Lien Restriction and Lien Recovery Fund Act, so confirm with counsel on residential work.

These notes summarize the statute as we read it.

Statutory sources: Utah Code §§ 38-1a-308, 38-1a-501, 38-1a-502, 38-1a-701. Read the Utah lien statute. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

File your Utah mechanics lien

We calculate the Utah deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Utah mechanics lien FAQ

How long do I have to file a mechanics lien in Utah?
The Utah lien must be recorded within 180 days after completion of the project. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Utah?
Required for every claimant, including the general contractor. Serve it on the state construction registry by any method that proves receipt. Missing it usually forfeits lien rights for the unnoticed work.
Does a Utah mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be verified by the claimant.
Where is a mechanics lien filed in Utah?
With the county recorder where the property sits. Electronic recording is available in participating counties, which typically cuts the turnaround to a day or two.
How long is a Utah mechanics lien valid?
A Utah lien must be enforced through a foreclosure lawsuit within 180 days after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Utah?
Yes. Subcontractors have lien rights in Utah, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.

This page summarizes Utah lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.