Massachusetts Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Massachusetts construction lien, drawn from M.G.L. c.254 §§ 4, 8, 11 (and §§2A–2B for substantial completion/termination notices) and the same rule engine that calculates deadlines for our filing customers.

Massachusetts lien rules at a glance

Preliminary notice
Required for every claimant, including the general contractor
Lien filing deadline
within 120 days after last furnishing labor or materials
Notarization
Required
The lien claim must be sworn to under oath
Where to record
Register of deeds for the county
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 90 days after the lien is recorded

Who can file a mechanics lien in Massachusetts

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Massachusetts.

Claimant Lien rights in Massachusetts
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Massachusetts mechanics lien deadlines

Required for every claimant, including the general contractor. Preliminary notices go to the property owner and the general contractor by certified mail.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 90 days after last furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 120 days after last furnishing labor or materials

Massachusetts does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Massachusetts lien

Recording the lien

Record with the register of deeds for the county. Electronic recording is not generally available, so build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.

After recording

Massachusetts does not require a separate notice after the lien is recorded, though most claimants send one anyway to prompt payment. To keep the lien alive it must be enforced by lawsuit within 90 days after the lien is recorded.

Wrongful lien exposure

Massachusetts exposes claimants who file an exaggerated or baseless lien to damages. M.G.L. c.254 §11: lien validity can be affected if claimant wilfully and knowingly claims more than due.

Practitioner notes for Massachusetts

Notice of Contract (subs/suppliers) deadline: file/record not later than earliest of (i) 60 days after Notice of Substantial Completion (§2A), (ii) 90 days after Notice of Termination (§2B), or (iii) 90 days after last furnishing by GC or those claiming through GC (M.G.L. c.254 §4). Sub-sub / lower-tier without direct contract with original contractor: lien amount can be limited unless Notice of Identification is sent to the original contractor within 30 days of commencing performance by certified mail RRR (c.254 §4). Statement of Account deadline: file/record not later than earliest of (i) 90 days after Notice of Substantial Completion, (ii) 120 days after Notice of Termination, or (iii) 120 days after last furnishing (c.254 §8). Enforcement: civil action to enforce lien must be commenced within 90 days after filing the §8 statement (c.254 §11). Also, an attested copy of the complaint must be recorded in the registry of deeds within 30 days after commencement of the action (c.254 §5/§11 practice—see guidance); not represented in this sheet.

Statutory sources: M.G.L. c.254 §§ 4, 8, 11 (and §§2A–2B for substantial completion/termination notices). Read the Massachusetts lien statute.

File your Massachusetts mechanics lien

We calculate the Massachusetts deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Massachusetts mechanics lien FAQ

How long do I have to file a mechanics lien in Massachusetts?
The Massachusetts lien must be recorded within 120 days after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Massachusetts?
Required for every claimant, including the general contractor. Serve it on the property owner and the general contractor by certified mail. Missing it usually forfeits lien rights for the unnoticed work.
Does a Massachusetts mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be sworn to under oath.
Where is a mechanics lien filed in Massachusetts?
With the register of deeds for the county. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a Massachusetts mechanics lien valid?
A Massachusetts lien must be enforced through a foreclosure lawsuit within 90 days after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Massachusetts?
Yes. Subcontractors have lien rights in Massachusetts, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.

This page summarizes Massachusetts lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.