Alaska Mechanics Lien
Deadlines & Filing Rules
Every notice, deadline, and recording requirement for an Alaska construction lien, drawn from AS 34.35.064, 34.35.068, 34.35.070, 34.35.071, 34.35.080 and the same rule engine that calculates deadlines for our filing customers.
Alaska lien rules at a glance
- Preliminary notice
- Not required to preserve lien rights
- Lien filing deadline
- within 120 days after last furnishing labor or materials
- Notarization
- Required
- The lien claim must be sworn to under oath
- Where to record
- County recorder where the property sits
- E-recording
- Varies by county
- Ask the recording office whether it accepts electronic recording before you rely on it.
- Enforcement deadline
- Within 6 months after the lien is recorded
Who can file a mechanics lien in Alaska
Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Alaska.
| Claimant | Lien rights in Alaska |
|---|---|
| General contractor (direct contract with the owner) | Yes |
| Subcontractor (hired by the general contractor) | Yes |
| Sub-subcontractor (hired by a subcontractor) | Yes |
| Material supplier to the owner | Yes |
| Material supplier to the general contractor | Yes |
| Material supplier to a subcontractor | Yes |
Alaska mechanics lien deadlines
Not required to preserve lien rights.
Calculate your Alaska deadlines
Enter your role and project dates to turn the rules below into calendar dates. For other states, use the mechanics lien deadline calculator.
Choose your role to see which dates you need.
Your deadlines
| Document | Who | Deadline |
|---|---|---|
| Passed |
liens are filed through the courts by an attorney. Get matched with a lien attorney.
We can prepare and record the lien for you before the deadline. Start your lien.
These dates come from the same rules our lien filing service uses. They are not moved for weekends or holidays. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.
Mechanics lien filing deadline
The last day the lien can be recorded against the property.
| Who | Project type | Deadline |
|---|---|---|
| All claimants | All projects | Within 120 days after last furnishing labor or materials |
Alaska does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.
Recording and enforcing an Alaska lien
Recording the lien
Record with the county recorder where the property sits. Whether electronic recording is accepted varies by county, so confirm with the recording office and build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.
After recording
Alaska does not require a separate notice after the lien is recorded, though most claimants send one anyway to prompt payment. To keep the lien alive it must be enforced by lawsuit within 6 months after the lien is recorded.
Wrongful lien exposure
Alaska exposes claimants who file an exaggerated or baseless lien to damages. A person injured by a violation of the lien statutes may sue for actual and consequential damages plus costs and reasonable attorney fees. A claimant who does not promptly remove a lien after full payment, or after learning it is mistaken, unjustified, premature or disproportionate, is liable for actual and consequential damages plus costs and attorney fees.
Practitioner notes for Alaska
In Alaska, a claim of lien must be recorded no later than 120 days after you complete your contract or stop furnishing labor, materials, services or equipment, as long as the owner has not recorded a notice of completion (AS 34.35.068(a)). If the owner does record a notice of completion, the window can shrink to 15 days after that recording for a claimant who had advance notice of it or who never gave a notice of right to lien (AS 34.35.068(b)). Giving a notice of right to lien under AS 34.35.064 can protect the longer period, so it is worth considering early on larger jobs. The claim must be verified by oath and state the property, owner, contractor, the work furnished, the amount due, and the last date you furnished (AS 34.35.070). Alaska has no counties; claims are recorded with the state recorder for the recording district where the property sits. A lien lasts six months after recording. To keep it, start a suit to enforce it within those six months, or record an extension notice in the same office within the original six months, which gives six more months (AS 34.35.080(a)). After suing, record a notice of the pending action to protect against later buyers (AS 34.35.080(c)). Release a lien promptly once paid or if it turns out to be mistaken or overstated. A claimant who does not can owe actual and consequential damages plus attorney fees (AS 34.35.074).
These notes summarize the statute as we read it.
Statutory sources: AS 34.35.064, 34.35.068, 34.35.070, 34.35.071, 34.35.080. Read the Alaska lien statute. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.
File your Alaska mechanics lien
We calculate the Alaska deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.
Alaska mechanics lien FAQ
How long do I have to file a mechanics lien in Alaska?
Do I need to send a preliminary notice in Alaska?
Does an Alaska mechanics lien need to be notarized?
Where is a mechanics lien filed in Alaska?
How long is an Alaska mechanics lien valid?
Can a subcontractor file a mechanics lien in Alaska?
More Alaska lien tools
This page summarizes Alaska lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.