Washington Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Washington construction lien, drawn from RCW 60.04.031, 60.04.091, 60.04.141, 60.04.171 and the same rule engine that calculates deadlines for our filing customers.

Washington lien rules at a glance

Preliminary notice
Required for subcontractors, sub-subcontractors, and suppliers
Lien filing deadline
within 90 days after last furnishing labor or materials
Notarization
Required
The lien claim must be sworn to under oath
Where to record
County recorder where the property sits
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 8 months after the lien is recorded

Who can file a mechanics lien in Washington

Lien rights depend on where you sit in the contracting chain. Tenant-ordered work can reach the owner's interest in Washington only where the owner consented to or required the improvements. Owner-occupied residential projects carry extra notice requirements in Washington; missing them can cost the lien entirely.

Claimant Lien rights in Washington
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Washington mechanics lien deadlines

Required for subcontractors, sub-subcontractors, and suppliers. Preliminary notices go to the property owner by any method that proves receipt.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 10 days after first furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 90 days after last furnishing labor or materials

Washington does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Washington lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is not generally available, so build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.

After recording

A copy of the recorded lien must be served on the property owner within 14 days of recording. To keep the lien alive it must be enforced by lawsuit within 8 months after the lien is recorded.

Wrongful lien exposure

In Washington, a wrongful lien claimant can be ordered to pay the owner's attorney fees and costs. RCW 60.04.081/171: frivolous lien motion; court may award costs and reasonable attorney fees; damages possible.

Practitioner notes for Washington

Residential notice: for owner-occupied single-family residences, certain lien claimants (notably material suppliers) must provide the statutory pre-claim notice (RCW 60.04.031). This sheet encodes a 10-day after first furnishing proxy; statute timing is tied to first delivery/provision and form content. Lien filing: record claim of lien within 90 days after last furnishing labor/materials/equipment (RCW 60.04.091). Serve copy of recorded claim of lien on the owner within 14 days after filing (RCW 60.04.091). Enforcement: commence action to foreclose within 8 months after claim filed (RCW 60.04.141). Frivolous lien remedies: motion to release + attorney fees (RCW 60.04.171).

Statutory sources: RCW 60.04.031, 60.04.091, 60.04.141, 60.04.171. Read the Washington lien statute.

File your Washington mechanics lien

We calculate the Washington deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Washington mechanics lien FAQ

How long do I have to file a mechanics lien in Washington?
The Washington lien must be recorded within 90 days after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Washington?
Required for subcontractors, sub-subcontractors, and suppliers. Serve it on the property owner by any method that proves receipt. Missing it usually forfeits lien rights for the unnoticed work.
Does a Washington mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be sworn to under oath.
Where is a mechanics lien filed in Washington?
With the county recorder where the property sits. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a Washington mechanics lien valid?
A Washington lien must be enforced through a foreclosure lawsuit within 8 months after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Washington?
Yes. Subcontractors have lien rights in Washington, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.

This page summarizes Washington lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.