Kentucky Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Kentucky construction lien, drawn from KRS §§ 376.010, 376.080, 376.090, 376.220 and the same rule engine that calculates deadlines for our filing customers.

Kentucky lien rules at a glance

Preliminary notice
Not required to preserve lien rights
Lien filing deadline
within 6 months after last furnishing labor or materials
Notarization
Required
The lien claim must be sworn to under oath
Where to record
County recorder where the property sits
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 1 year after the lien is recorded

Who can file a mechanics lien in Kentucky

Lien rights depend on where you sit in the contracting chain. Tenant-ordered work can reach the owner's interest in Kentucky only where the owner consented to or required the improvements. Owner-occupied residential projects carry extra notice requirements in Kentucky; missing them can cost the lien entirely.

Claimant Lien rights in Kentucky
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Kentucky mechanics lien deadlines

Not required to preserve lien rights. Kentucky requires a notice of intent to lien before the lien itself is recorded, served at least 120 days ahead of filing.

Notice of intent to lien

The final warning before a lien is recorded.

Who Project type Deadline
All claimants All projects At least 120 days before filing the lien

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 6 months after last furnishing labor or materials

Recording and enforcing a Kentucky lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is not generally available, so build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.

After recording

A copy of the recorded lien must be served on the property owner within 7 days of recording. To keep the lien alive it must be enforced by lawsuit within 1 year after the lien is recorded.

Wrongful lien exposure

Kentucky exposes claimants who file an exaggerated or baseless lien to damages. KRS §376.220(3): damages + reasonable court costs and attorney fees for filing in excess of amount actually due.

Practitioner notes for Kentucky

Pre-lien notice for non-direct claimants: notice of intent within 75 days (<$1,000) or 120 days (>$1,000) after last furnishing (KRS 376.010(4)); owner-occupied 1–2 family/ag/personal: notice within 75 days after last furnishing (KRS 376.010(5)) in lieu of (4). Tenant work: lessee not owner's agent unless owner designates in writing (KRS 376.010(1)(b)). Lien statement: file within 6 months after ceasing to labor/furnish; subscribed and sworn (KRS 376.080(1)). Mail copy to owner within 7 days of filing or lien dissolved (KRS 376.080(1)). Enforce within 12 months after filing (KRS 376.090(1)).

Statutory sources: KRS §§ 376.010, 376.080, 376.090, 376.220. Read the Kentucky lien statute.

File your Kentucky mechanics lien

We calculate the Kentucky deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Kentucky mechanics lien FAQ

How long do I have to file a mechanics lien in Kentucky?
The Kentucky lien must be recorded within 6 months after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Kentucky?
No. Kentucky does not require a preliminary notice to preserve lien rights, although sending one is still an effective way to get paid before a lien becomes necessary.
Does a Kentucky mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be sworn to under oath.
Where is a mechanics lien filed in Kentucky?
With the county recorder where the property sits. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a Kentucky mechanics lien valid?
A Kentucky lien must be enforced through a foreclosure lawsuit within 1 year after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Is a notice of intent to lien required in Kentucky?
Kentucky requires a notice of intent to lien before the lien itself is recorded, served at least 120 days ahead of filing.
Can a subcontractor file a mechanics lien in Kentucky?
Yes. Subcontractors have lien rights in Kentucky, and so do sub-subcontractors.

This page summarizes Kentucky lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.