North Carolina Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a North Carolina construction lien, drawn from N.C. Gen. Stat. §§ 44A-11.2, 44A-12, 44A-14, 44A-35 and the same rule engine that calculates deadlines for our filing customers.

North Carolina lien rules at a glance

Preliminary notice
Required for subcontractors, sub-subcontractors, and suppliers
Lien filing deadline
within 120 days after last furnishing labor or materials
Notarization
Not required
The lien claim must be verified by the claimant
Where to record
Clerk of the superior court for the county
E-recording
Varies by county
Ask the recording office whether it accepts electronic recording before you rely on it.
Enforcement deadline
Within 180 days after last furnishing labor or materials

Who can file a mechanics lien in North Carolina

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in North Carolina.

Claimant Lien rights in North Carolina
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

North Carolina mechanics lien deadlines

Required for subcontractors, sub-subcontractors, and suppliers. Preliminary notices go to the project lien agent by any method that proves receipt.

Calculate your North Carolina deadlines

Enter your role and project dates to turn the rules below into calendar dates. For other states, use the mechanics lien deadline calculator.

Project type

Choose your role to see which dates you need.

These dates come from the same rules our lien filing service uses. They are not moved for weekends or holidays. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 15 days after first furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 120 days after last furnishing labor or materials

North Carolina does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

How to file a North Carolina mechanics lien

The steps in order, each with the statute behind it. Some steps apply only to certain claimants, and each says so.

  1. 1

    Find the lien agent and send a Notice to Lien Agent

    On private projects costing $40,000 or more, the owner must name a lien agent (a registered title insurer). Its contact information appears on the posted building permit or a job-site sign, or the owner must supply it within 7 days of a written request. Deliver a Notice to Lien Agent no later than 15 days after you first furnish labor or materials. Delivery may be by certified mail, USPS signature confirmation, hand delivery with receipt, fax, a private delivery service, email with delivery receipt, or the lien agent's approved website (LiensNC). A late notice still works unless the property is sold to a good-faith buyer first, but the lien can fall behind loans recorded before the notice. The notice is not filed with the clerk.

    N.C. Gen. Stat. §§ 44A-11.1(a), 44A-11.2(b), (f), (i), (k), (l), (m)

  2. 2

    Second- and third-tier subcontractors: serve a Notice of Subcontract if a Notice of Contract was posted

    If the owner or contractor posted and filed a Notice of Contract within 30 days after the permit or contract award, a second- or third-tier subcontractor must serve a signed Notice of Subcontract on the contractor to keep its right to enforce the contractor's lien. Serve it by the methods in G.S. 44A-19(d) (personal delivery or any manner allowed by Civil Procedure Rule 4).

    N.C. Gen. Stat. § 44A-23(b)

  3. 3

    Subcontractors: serve a Notice of Claim of Lien upon Funds

    Subcontractors and suppliers who did not contract with the owner get a lien on funds owed down the payment chain. Perfect it by serving a Notice of Claim of Lien upon Funds, in the statutory form, on the owner and each obligor up the chain, by personal delivery or any manner allowed by Civil Procedure Rule 4. Once served, the owner must hold back the claimed amount from further payments. This notice is not filed with the clerk unless it is attached to a claim of lien on real property.

    N.C. Gen. Stat. §§ 44A-18, 44A-19, 44A-20

  4. 4

    Prepare the Claim of Lien on Real Property

    Use the statutory form titled Claim of Lien on Real Property. It is signed by the lien claimant and includes a certificate that the record owner has been served under G.S. 44A-11. The statute does not require notarization or a sworn verification. A subcontractor claiming through the contractor's lien adds the name of the contractor through which subrogation is asserted. A claim filed under G.S. 44A-20(d) must also attach the Notice of Claim of Lien upon Funds with an affidavit of service.

    N.C. Gen. Stat. §§ 44A-12(c), 44A-20(d), 44A-23

  5. 5

    File it with the clerk of superior court within 120 days

    File the claim in the office of the clerk of superior court in each county where the property is located, no later than 120 days after you last furnished labor or materials at the site. The clerk notes it on the judgment docket and indexes it under the record owner's name. It is a court filing, not a register of deeds recording. A filed claim cannot be amended; to fix it, cancel it and file a new one within the same 120 days.

    N.C. Gen. Stat. § 44A-12(a), (b), (d)

  6. 6

    Serve a copy on the record owner

    Perfecting the lien requires both filing and serving a copy of the claim on the record owner. Serve it by personal delivery, U.S. mail, or a designated private delivery service; actual receipt is not required. A correct address is the one on the building permit, on the county tax rolls, or the registered agent's address on file with the Secretary of State. Practitioners treat the 120-day filing window as the service window too.

    N.C. Gen. Stat. § 44A-11

  7. 7

    Sue to enforce within 180 days after last furnishing

    File suit to enforce the lien no later than 180 days after your last furnishing at the site, in any county where venue is proper. File a notice of lis pendens within the same period in every other county where the property lies. If the claim is filed on day 120, that leaves 60 days. Missing the deadline discharges the lien.

    N.C. Gen. Stat. §§ 44A-13(a), (c), 44A-16(a)(3)

What the claim of lien on real property must contain

North Carolina law requires the claim of lien on real property to include the following (N.C. Gen. Stat. § 44A-12(c)).

  • Name and address of the person claiming the lien
  • Name and address of the record owner at the time of filing, and, for a subrogation claim under G.S. 44A-23, the name of the contractor through which subrogation is asserted
  • Description of the real property (street address, tax lot and block, reference to a recorded instrument, or any description that reasonably identifies it)
  • Name and address of the person with whom the claimant contracted
  • Date labor or materials were first furnished by the claimant
  • Date labor or materials were last furnished by the claimant
  • General description of the labor performed or materials furnished, and the amount claimed (no itemized list required)
  • Certification that the parties listed in item 2 were served as G.S. 44A-11 requires
  • Signature of the lien claimant

The statute prescribes the form ('substantially as follows') rather than publishing a separate agency form; the text of the form is in G.S. 44A-12(c) at https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-12.html. No notarization or verification is required by the statute, and the NCBA Young Lawyers guide says a claim of lien does not need to be notarized. Claims under G.S. 44A-20(d) must attach the Notice of Claim of Lien upon Funds and proof of service by affidavit, and state why the owner is personally liable.

Download a blank North Carolina lien claim form

The Claim of Lien on Real Property our filing service prepares, with every field left blank. PDF, free, no sign-up. Fill in your own facts and check them against the list above before you sign.

Recording and enforcing a North Carolina lien

Recording the lien

Record with the clerk of the superior court for the county. Whether electronic recording is accepted varies by county, so confirm with the recording office and build mailing time into the deadline. No notary is required on the lien itself. The lien claim must be verified by the claimant.

After recording

A copy of the recorded lien must be served on the property owner and the general contractor promptly after recording. To keep the lien alive it must be enforced by lawsuit within 180 days after last furnishing labor or materials.

Wrongful lien exposure

Filing a knowingly false lien in North Carolina can carry criminal penalties as well as civil liability. Knowingly filing a claim of lien that is not authorized by statute, or filing one to hinder, harass, or wrongfully interfere with someone, is a Class I felony (§ 44A-12.1). In lien suits the court may also award reasonable attorney fees to the prevailing party (§ 44A-35, amended 2022).

Practitioner notes for North Carolina

North Carolina's lien law is in Chapter 44A, Article 2. On many private projects the owner must name a lien agent: generally where the improvement costs $40,000 or more, except work on an existing single-family home the owner lives in (G.S. 44A-11.1). On those projects, a claimant should get a Notice to Lien Agent to the lien agent within 15 days after first furnishing labor or materials (G.S. 44A-11.2). A later notice still works only if it arrives before a sale of the property to a good-faith buyer is recorded, and the lien can lose priority to loans recorded before the notice. Whether a contractor hired directly by the owner also needs to send this notice is debated in secondary sources, so confirm with counsel; most practitioners send it. A claim of lien must be filed in the office of the clerk of superior court in each county where the property sits, no later than 120 days after the claimant's last furnishing (G.S. 44A-12). It must be served as G.S. 44A-11 requires. It cannot be amended, only cancelled and refiled within the 120 days. The suit to enforce the lien must be filed within 180 days after last furnishing (G.S. 44A-13), which can leave as little as 60 days after the lien is filed. Knowingly filing a lien that no statute authorizes, or filing one to harass or wrongfully interfere with someone, is a Class I felony (G.S. 44A-12.1). The court may award reasonable attorney fees to the prevailing party in a lien suit (G.S. 44A-35).

These notes summarize the statute as we read it.

Statutory sources: N.C. Gen. Stat. §§ 44A-11.2, 44A-12, 44A-14, 44A-35. Read the North Carolina lien statute. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

Where to file in North Carolina

In North Carolina the claim of lien is filed with the clerk of superior court, not the register of deeds. The clerk's fee is set by statute for all 100 counties: $6 for the first page and $0.25 for each additional page (G.S. 7A-308(a)(11)). Ask the clerk whether it accepts claims of lien electronically before you rely on it.

The 10 most populous North Carolina counties, the office that takes liens in each, whether it accepts e-filing, and the fee it publishes. Liens on property in any other county go to that county's office.

County Office E-filing Fee
Wake Wake County Clerk of Superior Court
Wake County Courthouse, 316 Fayetteville St., Raleigh, NC 27601
Not stated
Ask the office
Statewide clerk fee for recording or docketing (including indexing) any document: $6.00 first page, $0.25 each additional page. Set by statute for all 100 counties. Fee schedule
Mecklenburg Mecklenburg County Clerk of Superior Court
832 E. Fourth St., Charlotte, NC 28202
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Guilford Guilford County Clerk of Superior Court
Guilford County Courthouse, 201 S. Eugene St., Greensboro, NC 27401
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Forsyth Forsyth County Clerk of Superior Court
Forsyth County Hall of Justice, 175 N. Chestnut St., Winston-Salem, NC 27101
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Durham Durham County Clerk of Superior Court
Durham County Justice Center, 510 S. Dillard St., Durham, NC 27701
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Cumberland Cumberland County Clerk of Superior Court
Judge E. Maurice Braswell Courthouse, 117 Dick St., Fayetteville, NC
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Buncombe Buncombe County Clerk of Superior Court
Buncombe County Courthouse, 60 Court Plaza, Asheville, NC 28801
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Union Union County Clerk of Superior Court
Union County Judicial Center, 400 N. Main St., Monroe, NC 28112
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
New Hanover New Hanover County Clerk of Superior Court
New Hanover County Courthouse, 316 Princess St., Wilmington, NC 28401
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule
Gaston Gaston County Clerk of Superior Court
Gaston County Courthouse, 325 Dr. Martin Luther King Jr. Way, Gastonia, NC 28052
Not stated
Ask the office
Statewide clerk fee under G.S. 7A-308(a)(11): $6.00 first page, $0.25 each additional page. Fee schedule

Collected from each office's website on October 2, 2026. Fees and filing methods change. Confirm them with the office before you file.

Recent changes to North Carolina lien law

Changes since 2022 that affect lien deadlines, notices, forms or filing.

S.L. 2022-1 (SB 219): progress-payment lien waivers limited

Effective March 1, 2022

New G.S. 22B-5 voids contract or waiver terms that require a lien waiver or release as a condition of an interim or progress payment, unless the waiver is limited to the payment actually received. Final-payment waivers and settlements of disputed claims are excepted. Applies to liens attached on or after March 1, 2022.

S.L. 2022-1, s. 3; N.C. Gen. Stat. § 22B-5

S.L. 2022-1 (SB 219): attorney fees in lien suits rewritten

Effective March 1, 2022

G.S. 44A-35 now lets the judge or an arbitrator award reasonable attorney fees to the prevailing party, defined as the party whose monetary position at the start of trial or hearing is closest to the judgment. A settlement offer or Rule 68 offer received at least 30 days before trial sets that party's position. Applies to claims arising on or after March 1, 2022.

S.L. 2022-1, s. 4; N.C. Gen. Stat. § 44A-35

S.L. 2023-108 (HB 488): lien agent threshold raised to $40,000

Effective October 1, 2023

The project cost at which an owner must designate a lien agent rose from $30,000 to $40,000, matching the new general contractor licensing threshold. Below $40,000, no Notice to Lien Agent is needed.

S.L. 2023-108, s. 2(h), (j); N.C. Gen. Stat. § 44A-11.1(a)

eCourts completed in all 100 counties

Effective October 13, 2025

The Judicial Branch finished converting every county to eCourts, with File & Serve electronic filing available statewide. Whether clerks accept claims of lien through File & Serve was not confirmed.

NC Judicial Branch press release, 'North Carolina Implements eCourts Conversion in All 100 Counties'

Sources for this page (17)

File your North Carolina mechanics lien

We calculate the North Carolina deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

North Carolina mechanics lien FAQ

How long do I have to file a mechanics lien in North Carolina?
The North Carolina lien must be recorded within 120 days after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in North Carolina?
Required for subcontractors, sub-subcontractors, and suppliers. Serve it on the project lien agent by any method that proves receipt. Missing it usually forfeits lien rights for the unnoticed work.
Does a North Carolina mechanics lien need to be notarized?
No. North Carolina does not require a notary on the lien itself. The lien claim must be verified by the claimant.
Where is a mechanics lien filed in North Carolina?
With the clerk of the superior court for the county. Whether electronic recording is accepted varies by county, so check with the recording office and allow time for mailing and processing when working back from your deadline.
How long is a North Carolina mechanics lien valid?
A North Carolina lien must be enforced through a foreclosure lawsuit within 180 days after last furnishing labor or materials. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in North Carolina?
Yes. Subcontractors have lien rights in North Carolina, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.
Can a supplier to a supplier file a lien in North Carolina?
Generally no lien on the land. Subcontractors down to the third tier can claim a lien on funds and, through subrogation, enforce the contractor's lien on the property. Tiers more remote than the third get a lien only on funds owed to the party they dealt with, with no subrogation (G.S. 44A-18(d)). Whether a pure materials supplier counts as a 'subcontractor' depends on whether it furnished materials at the site; confirm with counsel. Source: N.C. Gen. Stat. §§ 44A-7, 44A-18, 44A-23.
Can I file a lien on a public project in North Carolina?
No. Public property cannot be liened. On public projects whose contracts total more than $300,000 ($500,000 for state agencies and the UNC system), contractors must post a payment bond. A claimant who has not been paid 90 days after last furnishing may sue on the bond. Claimants who contracted only with a subcontractor must give the contractor written notice within 120 days after last furnishing. Suit must be filed within one year. Source: N.C. Gen. Stat. §§ 44A-26, 44A-27, 44A-28.
What does it cost to file a claim of lien in North Carolina?
Claims of lien are filed with the clerk of superior court, and the statewide fee for recording or docketing a document is $6.00 for the first page and $0.25 for each additional page. Serving the owner by certified mail or a delivery service adds postage. A Notice to Lien Agent sent through the LiensNC website is a separate step and is not filed with the clerk. Source: N.C. Gen. Stat. §§ 7A-308(a)(11), 44A-11, 44A-11.2(k).
How is a North Carolina lien released or discharged?
The claimant can acknowledge satisfaction before the clerk, or the owner can show the clerk a signed and acknowledged instrument of satisfaction. The lien is also discharged if not enforced in time, if the enforcement suit is dismissed or lost, or if the owner deposits cash equal to the claim or a surety bond for 1.25 times the claim with the clerk. Source: N.C. Gen. Stat. § 44A-16(a).
What happens after I file the claim of lien?
Serve a copy on the record owner to perfect the lien. The lien relates back to your first furnishing at the site, which gives it priority over later interests. You must file suit within 180 days after last furnishing and file a lis pendens in any other county where the property lies. A judgment directs a sale of the property, up to the amount stated in the claim. Source: N.C. Gen. Stat. §§ 44A-10, 44A-11, 44A-13(a)-(c).
What if I missed the 120-day deadline in North Carolina?
A claim of lien on real property filed more than 120 days after your last furnishing at the site is untimely and cannot be fixed by amendment. A subcontractor may still have a lien on funds, which is perfected by serving a notice on the owner or obligor and is not tied to the 120-day filing window. Payment bond rights may apply on public jobs. Get legal advice promptly. Source: N.C. Gen. Stat. §§ 44A-12(b), (d), 44A-18, 44A-19.