Every notice, deadline, and recording requirement for a California construction lien, drawn from Cal. Civ. Code §§ 8204, 8182, 8412, 8414, 8416, 8460, 8422 and the same rule engine that calculates deadlines for our filing customers.

California lien rules at a glance

Preliminary notice
Required for subcontractors, sub-subcontractors, and suppliers
Lien filing deadline
within 90 days after completion of the project
Notarization
Not required
The lien claim must be verified by the claimant
Where to record
County recorder where the property sits
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 90 days after the lien is recorded

Who can file a mechanics lien in California

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in California.

Claimant Lien rights in California
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

California mechanics lien deadlines

Required for subcontractors, sub-subcontractors, and suppliers. Preliminary notices go to the property owner, the general contractor, and the construction lender by certified mail.

Preliminary notice deadline

The notice that preserves lien rights before any payment problem exists.

Who Project type Deadline
All claimants All projects Within 20 days after first furnishing labor or materials

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 90 days after completion of the project

California does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a California lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is not generally available, so build mailing time into the deadline. No notary is required on the lien itself. The lien claim must be verified by the claimant.

After recording

A copy of the recorded lien must be served on the property owner and the general contractor promptly after recording. To keep the lien alive it must be enforced by lawsuit within 90 days after the lien is recorded.

Wrongful lien exposure

California exposes claimants who file an exaggerated or baseless lien to damages. Cal. Civ. Code §8422: willfully exaggerated claim can forfeit lien; claimant liable for damages and attorney fees.

Practitioner notes for California

Prelim (20-day) notice due within 20 days of first furnishing (Cal. Civ. Code §8204); late notice only preserves rights for work within 20 days before service. Direct contractors are generally exempt from prelim unless serving a construction lender (see Civ. Code §8200). Lien recording deadline: Direct contractor—before earlier of 90 days after completion or 60 days after Notice of Completion/Cessation recorded (§8412). Other claimants—before earlier of 90 days after completion or 30 days after Notice recorded (§8414). Notice of Completion must be recorded on/within 15 days after completion (§8182) to be valid. After recording lien, serve copy of the claim on the owner (Civ. Code §8416). Enforcement: file foreclosure action within 90 days after recordation (§8460), unless an extension of credit is recorded.

Statutory sources: Cal. Civ. Code §§ 8204, 8182, 8412, 8414, 8416, 8460, 8422. Read the California lien statute.

File your California mechanics lien

We calculate the California deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

California mechanics lien FAQ

How long do I have to file a mechanics lien in California?
The California lien must be recorded within 90 days after completion of the project. The same deadline applies to every claimant.
Do I need to send a preliminary notice in California?
Required for subcontractors, sub-subcontractors, and suppliers. Serve it on the property owner, the general contractor, and the construction lender by certified mail. Missing it usually forfeits lien rights for the unnoticed work.
Does a California mechanics lien need to be notarized?
No. California does not require a notary on the lien itself. The lien claim must be verified by the claimant.
Where is a mechanics lien filed in California?
With the county recorder where the property sits. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a California mechanics lien valid?
A California lien must be enforced through a foreclosure lawsuit within 90 days after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in California?
Yes. Subcontractors have lien rights in California, and so do sub-subcontractors. They must follow the preliminary notice rules to keep those rights.

This page summarizes California lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.