Tennessee Mechanics Lien
Deadlines & Filing Rules
Every notice, deadline, and recording requirement for a Tennessee construction lien, drawn from T.C.A. §§ 66-11-112, 66-11-115, 66-11-130, 66-11-143, 66-11-145 and the same rule engine that calculates deadlines for our filing customers.
Tennessee lien rules at a glance
- Preliminary notice
- Not required to preserve lien rights
- Lien filing deadline
- within 90 days after completion of the project
- Notarization
- Required
- The lien claim must be sworn to under oath
- Where to record
- Register of deeds for the county
- E-recording
- Varies by county
- Ask the recording office whether it accepts electronic recording before you rely on it.
- Enforcement deadline
- Within 1 year after project completion
Who can file a mechanics lien in Tennessee
Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Tennessee.
| Claimant | Lien rights in Tennessee |
|---|---|
| General contractor (direct contract with the owner) | Yes |
| Subcontractor (hired by the general contractor) | Yes |
| Sub-subcontractor (hired by a subcontractor) | Yes |
| Material supplier to the owner | Yes |
| Material supplier to the general contractor | Yes |
| Material supplier to a subcontractor | Yes |
Tennessee mechanics lien deadlines
Not required to preserve lien rights. Tennessee requires a notice of intent to lien before the lien itself is recorded, served at least 90 days ahead of filing.
Calculate your Tennessee deadlines
Enter your role and project dates to turn the rules below into calendar dates. For other states, use the mechanics lien deadline calculator.
Choose your role to see which dates you need.
Your deadlines
| Document | Who | Deadline |
|---|---|---|
| Passed |
liens are filed through the courts by an attorney. Get matched with a lien attorney.
We can prepare and record the lien for you before the deadline. Start your lien.
These dates come from the same rules our lien filing service uses. They are not moved for weekends or holidays. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.
Notice of intent to lien
The final warning before a lien is recorded.
| Who | Project type | Deadline |
|---|---|---|
| All claimants | All projects | At least 90 days before filing the lien |
Mechanics lien filing deadline
The last day the lien can be recorded against the property.
| Who | Project type | Deadline |
|---|---|---|
| All claimants | All projects | Within 90 days after completion of the project |
Recording and enforcing a Tennessee lien
Recording the lien
Record with the register of deeds for the county. Whether electronic recording is accepted varies by county, so confirm with the recording office and build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.
After recording
A copy of the recorded lien must be served on the property owner promptly after recording. To keep the lien alive it must be enforced by lawsuit within 1 year after project completion.
Wrongful lien exposure
In Tennessee, a wrongful lien claimant can be ordered to pay the owner's attorney fees and costs. If the court finds a lienor willfully and grossly exaggerated the lien amount, it may deny any recovery on the lien, and the lienor may be liable for the injured party's actual expenses, including attorney's fees. The older automatic-penalty statute, § 66-21-108, was repealed in 2019 (per secondary sources; repeal text not read).
Practitioner notes for Tennessee
Tennessee's lien statute is in Tennessee Code Title 66, Chapter 11. A prime contractor, meaning anyone with a contract directly with the owner, has a lien that lasts one year after the improvement is complete or abandoned. A suit to enforce it must be filed within that year (T.C.A. § 66-11-106). To protect its priority against later buyers and lenders, the prime should record a sworn notice of lien with the register of deeds within 90 days after completion or abandonment (§ 66-11-112). Subcontractors and suppliers further down the chain, called remote contractors, have more steps. Except on 1-4 family residential units, a remote contractor must serve a notice of nonpayment on the owner and on the prime contractor it worked under. The notice is due within 90 days after the last day of each month in which work or materials went unpaid, and missing it bars the lien except for retainage (§ 66-11-145). The remote contractor must also serve a notice of lien on the owner within 90 days after completion or abandonment. That lien lasts only 90 days after service, so suit must be filed within that time (§ 66-11-115). On an owner-occupied home of one to four units, generally only the prime contractor has lien rights (§ 66-11-146). An owner or prime contractor can serve a written demand that cuts the time to sue to 60 days (§ 66-11-130). If the owner records a notice of completion, remote contractors may have only 10 days (residential) or 30 days (other projects) to respond (§ 66-11-143). A lienor who willfully and grossly exaggerates the amount can lose the lien and owe the owner's attorney's fees (§ 66-11-139). Confirm with counsel on residential projects.
These notes summarize the statute as we read it.
Statutory sources: T.C.A. §§ 66-11-112, 66-11-115, 66-11-130, 66-11-143, 66-11-145. Read the Tennessee lien statute. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.
File your Tennessee mechanics lien
We calculate the Tennessee deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.
Tennessee mechanics lien FAQ
How long do I have to file a mechanics lien in Tennessee?
Do I need to send a preliminary notice in Tennessee?
Does a Tennessee mechanics lien need to be notarized?
Where is a mechanics lien filed in Tennessee?
How long is a Tennessee mechanics lien valid?
Is a notice of intent to lien required in Tennessee?
Can a subcontractor file a mechanics lien in Tennessee?
More Tennessee lien tools
- Free Tennessee lien waiver forms
- Tennessee notice of intent to lien
- Tennessee mechanics lien release
- Download a blank Tennessee lien claim form
- Mechanics lien deadline calculator
- Preliminary notice service
- Notice of intent to lien
- Payment demand letter
- Lien release
- Mechanics lien rules for every state
This page summarizes Tennessee lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.