Wyoming Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Wyoming construction lien, drawn from Wyo. Stat. §§ 29-2-106, 29-2-107, 29-2-109 and the same rule engine that calculates deadlines for our filing customers.

Wyoming lien rules at a glance

Preliminary notice
Not required to preserve lien rights
Lien filing deadline
within 150 days after completion of the project (varies by role)
Notarization
Required
The lien claim must be sworn to under oath
Where to record
County recorder where the property sits
E-recording
Not generally available; plan on paper recording
Enforcement deadline
Within 180 days after the lien is recorded

Who can file a mechanics lien in Wyoming

Lien rights depend on where you sit in the contracting chain. Tenant-ordered work can reach the owner's interest in Wyoming only where the owner consented to or required the improvements.

Claimant Lien rights in Wyoming
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Wyoming mechanics lien deadlines

Not required to preserve lien rights.

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
General contractors and suppliers to the owner All projects Within 150 days after completion of the project
Subcontractors, sub-subcontractors, suppliers to the general contractor, and suppliers to a subcontractor All projects Within 120 days after last furnishing labor or materials

Wyoming does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Wyoming lien

Recording the lien

Record with the county recorder where the property sits. Electronic recording is not generally available, so build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.

After recording

Wyoming does not require a separate notice after the lien is recorded, though most claimants send one anyway to prompt payment. To keep the lien alive it must be enforced by lawsuit within 180 days after the lien is recorded.

Wrongful lien exposure

Wyoming has no dedicated wrongful-lien penalty statute, but an inflated or baseless lien can still be challenged and removed at the claimant's expense.

Practitioner notes for Wyoming

Lien filing deadlines: original contractor must file lien statement within 150 days after completion of the contract; subcontractors/material suppliers generally within 120 days after last furnishing (see Wyo. Stat. §§29-2-106 & 29-2-107). Enforcement: action to enforce lien must be commenced within 180 days after filing the lien statement (Wyo. Stat. §29-2-109).

Statutory sources: Wyo. Stat. §§ 29-2-106, 29-2-107, 29-2-109. Read the Wyoming lien statute.

File your Wyoming mechanics lien

We calculate the Wyoming deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Wyoming mechanics lien FAQ

How long do I have to file a mechanics lien in Wyoming?
The Wyoming lien must be recorded within 150 days after completion of the project. The deadline differs by claimant role and project type, so check the table above for your situation.
Do I need to send a preliminary notice in Wyoming?
No. Wyoming does not require a preliminary notice to preserve lien rights, although sending one is still an effective way to get paid before a lien becomes necessary.
Does a Wyoming mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be sworn to under oath.
Where is a mechanics lien filed in Wyoming?
With the county recorder where the property sits. Paper filing is the norm, so allow time for mailing and the recorder's processing queue when working back from your deadline.
How long is a Wyoming mechanics lien valid?
A Wyoming lien must be enforced through a foreclosure lawsuit within 180 days after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Wyoming?
Yes. Subcontractors have lien rights in Wyoming, and so do sub-subcontractors.

This page summarizes Wyoming lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.