Vermont Mechanics Lien
Deadlines & Filing Rules

Every notice, deadline, and recording requirement for a Vermont construction lien, drawn from 9 V.S.A. §§ 1921, 1923, 1924, 1925 and the same rule engine that calculates deadlines for our filing customers.

Vermont lien rules at a glance

Preliminary notice
Not required to preserve lien rights
Lien filing deadline
within 120 days after last furnishing labor or materials
Notarization
Required
The lien claim must be sworn to under oath
Where to record
Town or city clerk
E-recording
Varies by county
Ask the recording office whether it accepts electronic recording before you rely on it.
Enforcement deadline
Within 180 days after the lien is recorded

Who can file a mechanics lien in Vermont

Lien rights depend on where you sit in the contracting chain. Tenant-ordered improvements can support a lien in Vermont.

Claimant Lien rights in Vermont
General contractor (direct contract with the owner) Yes
Subcontractor (hired by the general contractor) Yes
Sub-subcontractor (hired by a subcontractor) Yes
Material supplier to the owner Yes
Material supplier to the general contractor Yes
Material supplier to a subcontractor Yes

Vermont mechanics lien deadlines

Not required to preserve lien rights.

Calculate your Vermont deadlines

Enter your role and project dates to turn the rules below into calendar dates. For other states, use the mechanics lien deadline calculator.

Project type

Choose your role to see which dates you need.

These dates come from the same rules our lien filing service uses. They are not moved for weekends or holidays. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

Mechanics lien filing deadline

The last day the lien can be recorded against the property.

Who Project type Deadline
All claimants All projects Within 120 days after last furnishing labor or materials

Vermont does not require a notice of intent before recording a lien, but sending one is often what gets the invoice paid.

Recording and enforcing a Vermont lien

Recording the lien

Record with the town or city clerk. Whether electronic recording is accepted varies by county, so confirm with the recording office and build mailing time into the deadline. The lien must be notarized. The lien claim must be sworn to under oath.

After recording

A copy of the recorded lien must be served on the property owner within 5 days of recording. To keep the lien alive it must be enforced by lawsuit within 180 days after the lien is recorded.

Wrongful lien exposure

We found no dedicated wrongful-lien penalty in Vermont's lien statute. An owner can still ask a court to remove an inflated or baseless lien, so claim only what you are owed.

Practitioner notes for Vermont

Vermont's mechanics lien law is short and sits in 9 V.S.A. §§ 1921-1925. A contractor who works under an agreement with the owner, written or oral, has a lien on the improvements and the land (§ 1921(a)). A subcontractor or supplier hired by someone else gets a lien only by giving the owner written notice that it will claim one, including the payment due date if known. That lien reaches only the part of the contract price the owner still owes when the notice arrives, so send it early (§ 1921(b)). The lien lapses unless a written memorandum of lien is filed with the town clerk where the property is located within 180 days after payment became due for the last labor or materials (§§ 1921(c), 1923). Notice that the clock runs from the payment due date, not from your last day on site. To enforce, start a lawsuit and have the real estate attached within 180 days after filing the memorandum. If payment was not yet due when you filed, the 180 days run from when it becomes due (§ 1924). After you win, record a certified copy of the judgment with the town clerk within five months to foreclose like a mortgage (§ 1925). A lien cannot be waived before the work is done or the materials are delivered (§ 1921(f)). The statute asks only for a signed memorandum, but town clerks and practitioners commonly expect it notarized; confirm with counsel.

These notes summarize the statute as we read it.

Statutory sources: 9 V.S.A. §§ 1921, 1923, 1924, 1925. Read the Vermont lien statute. Deadlines turn on facts specific to your project. Confirm with counsel before relying on them.

File your Vermont mechanics lien

We calculate the Vermont deadlines from your project dates, prepare the lien on the correct form, and handle recording. Self-serve from $99, or full service with recording and notices handled for you from $299.

Vermont mechanics lien FAQ

How long do I have to file a mechanics lien in Vermont?
The Vermont lien must be recorded within 120 days after last furnishing labor or materials. The same deadline applies to every claimant.
Do I need to send a preliminary notice in Vermont?
No. Vermont does not require a preliminary notice to preserve lien rights, although sending one is still an effective way to get paid before a lien becomes necessary.
Does a Vermont mechanics lien need to be notarized?
Yes. The lien must be notarized before it is recorded. The lien claim must be sworn to under oath.
Where is a mechanics lien filed in Vermont?
With the town or city clerk. Whether electronic recording is accepted varies by county, so check with the recording office and allow time for mailing and processing when working back from your deadline.
How long is a Vermont mechanics lien valid?
A Vermont lien must be enforced through a foreclosure lawsuit within 180 days after the lien is recorded. If no suit is filed by then, the lien expires and can no longer be used to force payment.
Can a subcontractor file a mechanics lien in Vermont?
Yes. Subcontractors have lien rights in Vermont, and so do sub-subcontractors.

This page summarizes Vermont lien law for general information and is not legal advice. Deadlines depend on your role, project type, and dates; confirm them against the statute or with counsel before relying on them.