Tennessee Notice of Intent to Lien

Tennessee has no notice of intent before a lien. Its statutory notice is a notice of nonpayment. A remote contractor serves it within 90 days after the last day of each month in which work or materials went unpaid (Tenn. Code Ann. § 66-11-145).

Does Tennessee require a notice of intent to lien?

Not required. Tennessee has no notice of intent before a lien. Its statutory notice is a notice of nonpayment. A remote contractor serves it within 90 days after the last day of each month in which work or materials went unpaid (Tenn. Code Ann. § 66-11-145).

A notice of intent is a final written demand. It names the amount, the property and the date you will file. An owner who wants to keep a lien off the title has a clear reason to pay first, and you keep a dated record of the demand.

Notice of intent
Not required
Tenn. Code Ann. § 66-11-145
When to send it
None. Remote contractors serve a notice of nonpayment within 90 days after each unpaid month
Lien deadline
Within 90 days after completion of the project
Where the lien is filed
Register of deeds for the county
Free blank form
Yes, PDF
Notice of Intent to Record a Lien

Who sends it, to whom, and how

Who sends it
No one has to. Any claimant with lien rights can send one as a last demand before filing.
Who receives it
No law says. Our letter goes to the property owner and the general contractor.
How to send it
Send it by certified mail, return receipt requested, so you can prove when it arrived.

What a Tennessee notice of intent says

The notice our service prepares states the following. Keep it to facts you can prove.

  • Your name and the party you contracted with
  • The property, with its address and county
  • The labor or materials you furnished, and when
  • The amount unpaid
  • A demand to pay within 10 days, or you will file your notice of lien
  • Your signature and the date
Download a blank Tennessee notice of intent to lien

The Notice of Intent to Record a Lien our service prepares, with every field left blank. PDF, free, no sign-up. Fill in your own facts and check them against the rules on this page before you send it.

The Tennessee lien deadline it protects

The Tennessee lien deadline is within 90 days after completion of the project. The lien is filed with the register of deeds for the county. Send the notice early enough that the payment window ends before that deadline.

See every Tennessee lien deadline and filing rule

More Tennessee rules to know

  • The notice of nonpayment goes to the owner and to the prime contractor the remote contractor worked under. It is not required on one- to four-family residential units. Missing it bars the lien except for retainage (Tenn. Code Ann. § 66-11-145).
  • The free form on this page is a payment demand, not the notice of nonpayment.

Source: Tenn. Code Ann. § 66-11-145. Read the Tennessee lien statute. Notice rules turn on facts specific to your project. Confirm with counsel before relying on them.

Send your Tennessee notice of intent

We prepare the notice from your project details. Self-serve from $49: you review, sign and send it. Full service from $99: we send it to every party with proof of delivery.

Tennessee notice of intent FAQ

Is a notice of intent to lien required in Tennessee?
Tennessee has no notice of intent before a lien. Its statutory notice is a notice of nonpayment. A remote contractor serves it within 90 days after the last day of each month in which work or materials went unpaid (Tenn. Code Ann. § 66-11-145).
When do I send a Tennessee notice of intent to lien?
No law sets a time. Send it early enough that the 10-day payment window ends before you must file. The Tennessee lien deadline is within 90 days after completion of the project.
Who gets the notice, and how is it sent?
No law says. Our letter goes to the property owner and the general contractor. Send it by certified mail, return receipt requested, so you can prove when it arrived.
What does a Tennessee notice of intent to lien say?
Our letter states: your name and the party you contracted with; the property, with its address and county; the labor or materials you furnished, and when; the amount unpaid; a demand to pay within 10 days, or you will file your notice of lien; your signature and the date.
Is there a free Tennessee notice of intent to lien form?
Yes. Download the blank Notice of Intent to Record a Lien on this page. It is the same notice our service prepares, with every field left blank. Or we prepare and send it for you from $49.

This page summarizes Tennessee law for general information and is not legal advice. Notice and release rules depend on your role, project type and dates. Confirm them against the statute or with counsel before relying on them.